We will shortly be commencing work to replace the Chris Anderson Stadium athletics track as the current track has reached the end of its lifespan. The track will be replaced with a brand new surface matching that of the indoor athletics area.

We have now reached an agreement with our preferred contractor and dates of work will be:

Work commences: Monday 9th March 2015
Anticipated completion: Friday 22nd May 2015

Clearly this timetable is weather dependant, but we are hopeful this can be achieved. During this time the entire track and infield will not be available – the indoor athletics area will remain available to members and we will look to make other areas, such as the hockey pitch, available for training where possible.

We appreciate that there will be disruption during these works, but the end result will be one of the best facilities in the country in time for the summer.

If you have any queries please do not hesitate to contact us – we will keep you updated as work progresses.